Project Timeline

Feasibility Study Project

Kick Off w/ Steering Committee

MARCH 2020

Market Research,

Outreach Strategy Development

APRIL 2020

concept-1868728_1920.jpg
OHV Single Logo.png

Start Feasibility Study

MAY 2020

change-948020_1920.jpg

JUNE 2020

Dollar Bills

AUGUST 2020

Creation & Analysis of GIS Data

GIS Map thumbnail.JPG

TECHNICAL FEASIBILITY STUDY PHASE

Summary of Impact on Local Economy

DECEMBER 2020

Economy News

JANUARY 2021

a27d24_1b5877d9933142ac9dbc5299c77da1d4~

Tier 2 Analysis of 12 Sites to 6

FEBRUARY 2021

a27d24_1b5877d9933142ac9dbc5299c77da1d4~

Tier 2 Site Selection Draft Report,

Identification of Potential Partners and Funders

MARCH 2021

Business Meeting

Tier 3 Analysis of 6 Sites to 3,

Initiate Stakeholder/Land Owner Outreach

APRIL 2021

a27d24_1b5877d9933142ac9dbc5299c77da1d4~

Stakeholder Input

MAY 2021

plans

All Tiers Draft Report

All Tiers Final Report

DECEMBER 2021

Desk

Initiate Public Engagement

Virtual Open House 1/27/2022

JANUARY 2022

OHV Information Flyer Final.jpg

Initial Survey Responses close 

February 14, 2022

FEBRUARY 2022

feedback-1825515_1920.jpg

Initiate Community Outreach Meetings for Top 3 ranked sites including Stakeholders and surrounding property owners.

SPRING 2022

board-4874863_1920.jpg

PUBLIC ENGAGEMENT & DUE DILIGENCE PHASE

Apply for additional Planning Grant Funding for Environmental Review Process

SPRING 2022

dollar-1362243_1920.jpg

Project Site and Alternatives Selection

FALL 2022

extreme-4502198_1920_edited.jpg

2023-2025 Environmental

2025 Public review for environmental

laptop-2055522_1920.jpg

2025-2029

 Acquisition 

desert-5009555_1920_edited.jpg

2026-2032 Design and Construction

buggy-5259814_1920.jpg

Currently Proposed Schedule*

*subject to change and pending funding